Economy October 11, 2018 - 3:15 pm

Power plant of scandal undergoes first test run today

Santo Domingo.- State Electric Utility (CDEEE) CEO Rubén Jiménez Bichara on Thursday said the Punta Catalina power plant will undergo its first test run at 3pm today.

Recently the U.S.-based company Xcoal Energy won the tender to supply 462,000 metric tons of coal to fuel Punta Catalina during its trial period, starting November.

The scandal-fraught facility Punta Catalina features two generators of 376 megawatts each, located near Baní, southern Peravia Province.

Being built by the notorious Brazilian company Odebrecht, the facility is at the center of a scandal on alleged ballooned cost as high as US$1.2 billion.

COVID-19

May 10, 2024 - 2:16 pm

Bioanalysts union appeals to President Abinader for improved conditions

May 10, 2024 - 10:17 am

Ministry of Public Health issues alert for flood-related diseases

May 5, 2024 - 9:36 am

287 people arrested in Los Haitises for environmental crimes

April 30, 2024 - 10:04 am

SeNaSa hires more than 1,500 doctors

MOST READ

People

Celinee Santos crowned Miss Dominican Republic Universe 2024

Tourism

Cuba shows interest in exploring opportunities in Dominican tourism

Local

Scientific study reveals oil generation potential in Dominican Republic’s basins

Expats' Corner

Tips for couples making the Big Move to the Dominican Republic

MORE NEWS

Local

Building a home becomes more difficult; the ICDV rose 38%

Local

Those affected by the rains come back to life

Local

After complaints from residents, the SDE Mayor’s Office carries out a cleaning and waste collection day

Local

Indrhi says dam flows increase due to storm rains